Labor Unit Hours: Mold
Remediation |
|
Discipline |
Unit |
Hours Per
Unit |
|
A/C Unit - (portable spot) - set-up |
Each |
0.20 - 0.65 |
|
Air Filtration Device - equipment
set-up with up-to 20
LF lay-flat |
Each |
0.40 - 1.00 |
|
Anti-Microbial encapsulate - (brush) |
100 SF |
0.35 - 0.65 |
|
Anti-Microbial encapsulate - (spray) |
100 SF |
0.30 - 0.60 |
|
|
|
Cover penetrations - poly/tape - (up to - 1 SF) |
Each |
0.30 - 0.40 |
|
Cover penetrations - poly/tape - (up to - 3 SF) |
Each |
0.35 - 0.45 |
|
Cover penetrations - poly/tape - (up to - 10 SF) |
Each |
0.40 - 0.55 |
|
Decontamination unit -
pre-fabricated - set-up |
Each |
0.40 - 0.75 |
|
Demolition, see;
Labor Unit Hours Demolition
and add 4% to 15% per unit listed, based on the degree
of difficulty. |
|
Dry Ice (CO2) blasting machine -
equipment set-up |
Each |
0.65 - 1.65 |
|
Dry Ice (CO2) blasting - plywood |
100 SF |
2.00 - 4.85 |
|
Dry Ice (CO2) blasting - 2x4 wood |
100 LF |
1.15 - 2.20 |
|
Dry Ice (CO2) blasting - 2x6 wood |
100 LF |
1.17 - 2.22 |
|
Dry Ice (CO2) blasting - 2x8 wood |
100 LF |
1.19 - 2.25 |
|
Dry Ice (CO2) blasting - 2x10 wood |
100 LF |
1.25 - 2.45 |
|
Dry Ice (CO2) blasting - 2x12 wood |
100 LF |
1.35 - 2.55 |
|
Gather debris and double-bag - (3
CF bag - includes wiping bag) |
Each |
0.15 - 0.25 |
|
HEPA vacuum floor -
(smooth) |
100 SF |
0.45 - 1.15 |
|
HEPA vacuum wall - (smooth) |
100 SF |
0.65 - 1.55 |
|
|
|
Install 4 mil polyvinyl - floor - (includes tape
& adhesive) |
100 SF |
0.65 - 0.85 |
|
Install 4 mil polyvinyl - wall - (up to 8
VLF) - (includes tape
& adhesive) |
100 SF |
0.75 - 1.15 |
|
Install 4 mil polyvinyl - wall- (9 VLF - 20 VLF)
- (includes tape & adhesive) |
100 SF |
0.85 - 1.20 |
|
Install 6 mil polyvinyl - floor - (includes tape
& adhesive) |
100 SF |
0.70 - 0.95 |
|
Install 6 mil polyvinyl - wall - (up to 8 VLF) - (includes tape
& adhesive) |
100 SF |
0.80 - 1.25 |
|
Install 6 mil polyvinyl - wall - (9 VLF - 20 VLF) - (includes tape
& adhesive) |
100 SF |
0.90 - 1.35 |
|
Sand or wire brush 2x4 wood |
100 LF |
2.00 - 2.95 |
|
Sand or wire brush 2x6 wood |
100 LF |
2.15 - 3.10 |
|
Sand or wire brush 2x8 wood |
100 LF |
2.20 - 3.20 |
|
Sand or wire brush 2x10 wood |
100 LF |
2.30 - 3.55 |
|
Sand or wire brush 2x12 wood |
100 LF |
2.35 - 3.75 |
|
Wet wipe drop ceiling suspension
system (2x4) |
100 SF |
0.35 - 0.55 |
|
Wet wipe floor (mopping) |
100 SF |
0.25 - 0.35 |
|
Wet wipe metal joist - open web -
(up to - 12")
- (10' - 16'
AFF) |
100 LF |
0.67 - 1.10 |
|
Wet wipe metal joist - open web -
(up to - 24") - (16' - 22' AFF) |
100 LF |
1.00 - 1.25 |
|
Wet wipe metal roof decking -
corrugated |
100 SF |
1.25 - 2.25 |
|
Wet wipe metal stud - 2-1/2" - (up to 8 VLF) |
100 LF |
0.15 - 0.22 |
|
Wet wipe metal stud - 3-5/8" - 4"
- (up to 8 VLF) |
100 LF |
0.17 - 0.27 |
|
Wet wipe metal stud - 6" - (up to 8 VLF) |
100 LF |
0.25 - 0.33 |
|
Wet wipe wall - (up to 8 VLF) - |
100 SF |
0.20 - 0.33 |
|
Wet wipe wall - (9 VLF - 16 VLF) |
100 SF |
0.33 - 0.43 |
|
Labor hours listed above are based
on skilled labor, and will vary outside of the Hours Units
shown due to; surface conditions, job site conditions, temperature and humidity
levels, working height, quantity of materials, type - quality and condition of tooling,
lighting, etc.
The p1m.com
Disclaimer pertains to the Labor Unit Hours within this section
and all Labor Unit Hour within p1m.com. |