Labor
Unit Hours: Rough Carpentry - Framing |
|
Wood Framing
|
|
Discipline |
Unit |
Hours Per
Unit |
|
Bridging - metal |
20 Sets |
1.00 |
|
Bridging - wood 1x3 cut on job site |
8 Sets |
1.00 |
|
Bridging - wood 1x3 redi cut |
15 Sets |
1.00 |
|
Bridging - wood solid |
10 Pieces |
1.00 |
|
Furring on masonry - (includes shimming) |
100 LF |
4.00 |
|
Furring on stud wall - (includes shimming) |
100 LF |
3.00 |
|
Girders - Built Up from 2" stock |
1,000
FBM |
16.00 - 20.00 |
|
Joists 2x6 - 16" O.C. |
1,000 FBM |
18.00 - 22.00 |
|
Joists 2x8 - 16" O.C. |
1,000 FBM |
18.00 - 22.00 |
|
Joists 2x10 - 16" O.C. |
1,000 FBM |
18.00 - 20.00 |
|
Joists 2x12 - 16"
O.C. |
1,000 FBM |
18.00 - 21.00 |
|
|
|
Rafters 2x6 - flat roof |
1,000 FBM |
26.00 - 30.00 |
|
Rafters 2x8 - flat roof |
1,000 FBM |
26.00 - 30.00 |
|
Rafters 2x6 - plain gable roof |
1,000 FBM |
27.00 - 31.00 |
|
Rafters 2x8 - plain gable roof |
1,000 FBM |
21.00 - 31.00 |
|
Rafters 2x6 - plain hip roof |
1,000 FBM |
28.00 - 33.00 |
|
Rafters 2x8 - plain hip roof |
1,000 FBM |
28.00 -33.00 |
|
Sills and plates bolt and grout |
1,000 FBM |
20.00 - 24.00 |
|
Stud wall - wood - 2x4 - 16" O.C. |
1,000 FBM |
18.00 - 24.00 |
|
Stud wall - wood - 2x6 - 16" O.C. |
1,000 FBM |
20.00 - 24.00 |
|
Metal Framing
Top
of Page |
|
Discipline |
Unit |
Hours Per
Unit |
|
Black iron |
100 LF |
2.25 - 4.55 |
|
2-1/2" - Metal stud 16" O.C. wall - 8' high |
100 LF |
18.55 - 22.00 |
|
3-5/8" - Metal stud 16" O.C. wall - 8' high |
100 LF |
19.00 - 31.75 |
|
6" - Metal stud 16" O.C. wall - 8' high |
100 LF |
23.25 - 34.00 |
|
2-1/2" - Metal stud 16" O.C. wall - 10' high |
100 LF |
20.50 - 22.55 |
|
3-5/8" - Metal stud 16" O.C. wall - 10' high |
100 LF |
22.00 - 32.25 |
|
6" - Metal stud 16" O.C. wall - 10' high |
100 LF |
23.75 - 33.55 |
|
|
|
Wood blocking 2x6 |
100 LF |
16.00 - 23.00 |
|
Labor hours listed above are based
on skilled labor, and will vary outside of the Hours Units
shown due to; surface conditions, job site conditions, temperature and humidity
levels, working height, quantity of materials, type - quality and condition of tooling,
lighting, etc.
The p1m.com
Disclaimer pertains to the Labor Unit Hours within this
section and all Labor Unit Hour within p1m.com. |