Labor
Unit Hours: Demolition
(labor unit hour do not include gathering and carting of debris) |
|
Discipline |
Unit |
Hours Per
Unit |
|
Block - wall |
100 SF |
5.00 - 6.25 |
|
Cabinet - base |
10 LF |
1.55 - 3.25 |
|
Cabinet - wall |
10 LF |
2.00 - 4.45 |
|
Carpet - glued |
100 SF |
0.35 - 1.25 |
|
Cart debris to dumpster (includes gathering
debris) |
10 CY |
3.95 - 8.95 |
|
Casing - baseboard - door/window trim (3-1/2) |
100 LF |
1.00 - 1.55 |
|
Ceiling suspension system - (2x4) |
100 SF |
1.50 - 2.25 |
|
Ceiling tile - lay in - 2x4 (no-insulation
above) |
100 SF |
0.25 - 0.75 |
|
Ceiling tile - (12x12) |
100 SF |
0.75 - 2.00 |
|
Concrete slab - 4" - no-rebar |
100 SF |
7.50 - 9.00 |
|
Counter top w/ back splash |
10 LF |
0.75 - 1.25 |
|
|
|
Door - entry - metal - 3-0 |
Each |
0.55 - 0.75 |
|
Door - hollow-core - 3-0 |
Each |
0.30 - 0.55 |
|
Door - overhead - (8x8x1-3/8) |
Each |
1.95 - 3.95 |
|
Door - overhead - (15x7x1-1/4) |
Each |
3.00 - 5.95 |
|
Door - wood - solid-core - 3-0 |
Each |
0.60 - 1.10 |
|
Floor tile - ceramic - 12x12 |
100 SF |
1.75 - 3.55 |
|
Floor - hardwood - 3/4" - 1" |
100 SF |
2.25 - 3.15 |
|
Floor tile - VCT - 12x12 |
100 SF |
1.55 - 2.55 |
|
Floor - sub-floor - plywood |
100 SF |
1.20 - 2.25 |
|
Framing - metal studs only (3-5/8) - 16" O.C.
- (non-load-bearing) |
100 SF |
0.20 - 0.55 |
|
Framing - wood studs only (2x4) - 16" O.C. -
(non-load-bearing) |
100 SF |
0.35 - 0.65 |
|
Gutter - downspout |
100 LF |
3.30 - 4.25 |
|
Gypsum board - ceiling - (3/8 - 1/2) |
100 SF |
2.25 - 3.25 |
|
Gypsum board - wall - (3/8 - 1/2) |
100 SF |
1.65 - 2.20 |
|
Gypsum board - ceiling - 5/8 |
100 SF |
2.75 - 4.25 |
|
Gypsum board - wall - 5/8 |
100 SF |
1.85 - 2.55 |
|
|
|
Roof - built up - flat |
100 SF |
2.00 - 5.35 |
|
Roof - sheeting - 1/2" |
100 SF |
1.45 - 2.00 |
|
Roof - shingles asphalt (25lb) |
100 SF |
1.00 - 1.55 |
|
Siding - aluminum |
100 SF |
1.55 - 2.25 |
|
Siding - wood |
100 SF |
1.15 - 2.25 |
|
Window - double-hung - (3x5) |
Each |
0.50 - 1.00 |
|
Window - picture - (4x7) |
Each |
1.25 - 2.25 |
|
Labor hours listed above are based
on skilled labor, and will vary outside of the Hours Units
shown due to; surface conditions, job site conditions, temperature and humidity
levels, working height, quantity of materials, type - quality and condition of tooling,
lighting, etc.
The p1m.com
Disclaimer pertains to the Labor Unit Hours within this
section and all Labor Unit Hour within p1m.com. |